|
Shaft Sinking
A shaft may be described as
a vertical or inclined tunnel from surface for conveyance of men, materials,
ventilation, pumping water, in addition to hoisting ore and waste rock.
During the life of the Cost
Book there were six shafts being sunk from time to time at Wheal Agar. The two important
ones were New Engine and Windstraw Shafts. The others were Boundary and
Dobree's shafts, and three unnamed exploration or ventilation shafts.
New
Engine Shaft
At the time of the
commencement of the Cost Book in October 1855 the shaft bottom was just below
the 24 fathom level. A pare of James Pope & Co. consisting of 9 men, were
sinking at a rate of 4.5 metres per month at a price of £18 per fathom.
We do not know the
dimensions of this shaft but it was probably no larger than 2.4 metres by 2.0
metres. The number of men in the pare would perhaps indicate that they worked
on 3 shifts with intervals for fume clearance after blasting.
By the end of December 1855
James Pope & Co. had reached the 36 fathom level and their price had been
increased to £22 per fathom. They met some water problems in November and
were awarded with an additional £0.58 for baling the water up to the adit level.
At this point it should be
noted that the Company had bought a second hand Cornish Engine from Penhale Mine, and during October James Nicholls and
another man had started dismantling it at a cost of £6.50. This engine had
been selected for the New Engine Shaft. The details and costs of
dismantling, carriage to Wheal Agar and installation are all recorded in the
Cost Book. This will be summarised under the section named 'Building Engine
Houses'.
36
fathom to 48 fathom
Meanwhile in January 1856 James
Pope & Co were cutting a plat of 7 metres at the 36 fathom level for
which they were paid £34.50 for the month with an additional £6 for planking and
dividing the shaft. Sinking did not start again until March because the pare
were engaged in 'cutting ground at the adit level and taking up water', and earned another £3. This work was probably to make room for a whim for
drawing water from the shaft bottom during sinking and which they erected in
February. In the same month the pare also advanced a drive for 5 and 3
metres north and south respectively, but perhaps more correctly they were
cross-cuts to intersect the north and south lodes.
Sinking the shaft started
again in March 1856 but not before they had erected a penthouse and hanging
tackle. Penthouse is the Cornish name for pentice which is a timber protection
installed across the shaft for the safety of the shaft sinkers underneath.
The penthouse would have had a trap door through which the shaft sinkers and
kibbles could pass.
Three more men were added
to the pare in March and in July the 48 fathom level had been reached with a
record sinking speed in May of 5.95 metres, the contract price during the last
three months being £26 per fathom.
48
fathom to 60 fathom
In August 1856 the same
routine was carried out as in February with cutting a plat, removing the old
penthouse and putting in a new one under the 48 fathom level, and also driving
a short distance north from the plat. However a different pare under
the name of William Wearne & Co took over the work and in September they obtained a
much higher price of £44 per fathom.
Sinking continued for the
next few months until February 1857 when they holed through to a crosscut on the
60 fathom level driven from an older shaft. For this they received a bonus
of £1.80 and it increased their take home pay for the month to £46.98 between the twelve men.
60
fathom to 70 fathom
Having reached the 60
fathom level they needed to sink a little further to make room for a penthouse
underneath. The 60 fathom plat was not completed until May 1857 and this
permitted drives to be started in both east and west directions along the north
lode.
While the shaft was being
sunk it was also being widened from surface down to the 36 fathom level to make
room for a 'skip road'. The traditional method of hoisting rock was by horse whim and kibbles. With the purchase of the new Cornish engine the decision
had been made to use the engine both for pumping water and also hoisting skips,
the latter replacing the kibbles. A skip is a container for hoisting rock,
usually running on rails. (Please refer to the
Glossary page
for clarification of mining terms).
In May 1857 William Wearne
and his pare of twelve men continued sinking the shaft down to the 70 fathom
level which they reached in January 1858. With the increased depth the value of the contract varied between
£40 and £46 per fathom.
Before the pare could
continue the sinking many jobs had to be done, such as cutting bearer holes for
a cistern in the shaft at the 70 fathom level, cutting a plat, putting in
a new penthouse and removing the old one above. They also did some stoping
which would indicate that the shaft had either intersected the ore, or was
following it.
70
fathom to 81 fathom
The sinking commenced again
in April of 1858 with William Wearne & Co and an additional six boys for 'drawing
water'. By December of the same year the pare had sunk another 11
metres after which sinking was then halted, and did not resume during the life
of the Cost Book.
Summary
of Sinking in New Engine Shaft
1st October 1856 to
31st December 1858. (39 months)
|
Depth sunk |
 |
105 metres |
|
Sinking rate
for 33 months |
|
3.18 metres per
month |
|
Gross Pay to
miners |
|
£2380 |
|
Net pay |
|
£1935 |
|
Cost of stores |
|
£ 445 |
|
Cost per metre
|
|
£
22.70 |
Windstraw Shaft
This shaft was first mentioned in the Cost
Book in February 1856, in an entry concerning a winze being sunk under the 33
fathom level on Wheal Fortune Lode east of Windstraw Shaft. The spelling
of this name in some other records has been shown as Windstow, but I will keep
the spelling as given in the Cost Book.
This shaft was at the Eastern end of the Wheal
Agar sett and the photograph below shows what I think is the location of the
burrow to the east of Chariot Road:-

Carn Brea is in the background with the
monument to Lord Francis Basset clearly seen in the centre.
In March 1856 a pare with the name of Richard
Luke & Co. (6 men), began sinking the shaft under the 33 fathom level. The
price per fathom was set at £6 per fathom which was considerably less than New
Engine Shaft, and probably it was a smaller cross section. In April the
price was set at £9 and it increased again in May to £13 per fathom. It would
appear also that the shaft may have been sunk in the lode as an entry in the
Cost Book says 'copper ore bought of them' (sic) and for which they were paid
£1.15.
In June 1856 a different pare of 6 men under the
name of John Goldsworthy & Co. took over the sinking, and were followed in July
by another pare of 6 men under the name of Jos/h Gribble & Co. Whether Jos/h
stands for Josiah, Joseph or Joshua I do not know as it is always abbreviated as
shown. This pare completed the sinking to the 40 fathom level, after which
they did some widening of the shaft, cut a plat and commenced driving west with
4 men until July 1857. They reached a point 63 metres west of the shaft
and one wonders what the air must have been like at this dead end with smoke from tallow
candles and gunpowder fumes. There is no confirmation that connections were made
to any winzes from the level above or older workings, nor any mention of air
sollars being installed.
40 fathom to 50 fathom
During the previous five months of work to
reach the 40 fathom level the average monthly
sinking rate was 4 metres. While the east and west drives were being
driven from the 40 fathom level the sinking operation was suspended until May
1857 when a pare of 4 men in the name of Josiah Angove & Co. put in a penthouse
and made a start on the next sinking cycle. He added two more men to his pare
and they reached the 50 fathom level in October 1857 averaging 4 metres per
month.
Here the sinking was again suspended for seven
months while drives were driven east and west to a distance of 36 metres, and at
the same time winzes were being sunk from the 40 fathom level above.
In April and May 1858 some stoping was carried
out in the bottom of the shaft at a rate of 15 shillings per fathom, and
presumably this should have read 'per square fathom'. When this was
completed the entry in the Cost Book for June reads 'Clearing shaft, taking
up water, putting in Penthouse, hanging tackle etc' (sic).
50 fathom to 56 fathom
In June 1858 Josiah Angove & Co. and his pare
of 6 men began sinking again at a rate of £15 per fathom and this was increased
to £16 in July. Then in August another 6 men joined the pare with the rate
increased to £17 per fathom and by the end of the month they had sunk 10.5
metres since June.
50 fathom to 56 fathom
In June 1858 Josiah Angove & Co. and his pare
of 6 men began sinking again at a rate of £15 per fathom and this was increased
to £16 in July. Then in August another 6 men joined the pare with the rate
increased to £17 per fathom and by the end of the month they had sunk 10.5
metres since June. At this point sinking was stopped and a decision was made to
install an engine for both pumping and winding. This necessitated widening of the
shaft to make room for a skip road, and in November work started from surface
described as 'Cutting down and securing Windstraw Shaft'.
By the end of April 1859 the engine had been
installed and commenced working, with a new name given to the shaft as Eastern
Engine Shaft.
56 fathom to 60 fathom
In May
sinking started again with a pare of 9 men under the name
of William Hosking & Co. and during the month they sank 4.65 metres at a rate of
£20 per fathom. They obviously came across some good ore and spent the
month of June in stoping at a rate of £1.30 per square fathom, as well as
putting in more of the skip road.
Sinking began again in July by the same pare
and reached the 60 fathom level after 3.05 metres. During August the pare began
driving east and west, as well as 'putting in sollar and footway for bargain',
and also 'watching engine'. the pare being assisted by 3 boys.
60 fathom and under
In September 1859 the same
pare sank another 4.27 metres as well as 'casing down shaft', 'hanging tackle'
and 'watching engine'. Lastly in October and November with 9
men and 3 boys they made 8.53 metres and continued 'casing down shaft'
as well as putting in a penthouse under the 60 fathom level. What
happened after this we will need to find in the new cost book if it is still in
existance.
Summary of sinking in
Windstraw (Eastern Engine Shaft)
March 1856 to November 1859
(45 months)
|
Depth sunk
|
 |
71.70 metres |
|
Sinking rate for 19 months |
|
3.77 metres
|
|
Gross pay to miners
|
|
£1217 |
|
Net pay
|
|
£
971 |
|
Cost of stores |
|
£ 246
|
|
Cost per metre
|
|
£
17 |
Sinking other shafts
Boundary Shaft.
This shaft was located at the east of the
sett on the boundary with Wheal Tehidy. It had reached the 40 fathom level by
the start of the Cost Book in October 1855, and was sunk intermittently from
then on.
Summary of sinking in Boundary
Shaft
|
Depth sunk
|
 |
24.52 metres |
|
Sinking rate for 5 months |
|
4.90 metres
|
|
Gross pay to miners
|
|
£135 |
|
Net pay
|
|
£ 95 |
|
Cost of stores |
|
£ 40
|
|
Cost per metre
|
|
£
5.50 |
Other Shafts
Dobree's Shaft.
A small amount of sinking was carried out
in July, September and October 1857 to take the shaft below the 40 fathom level.
The average advance per month was 4.31 metres at a cost of £3.78 per metre.
Miscellaneous Shafts
There were two exploration or ventilation
shafts sunk under adit level, the first entries being in November and December
1857, and the second in May and June 1858. A total of 16.31 metres were
sunk with an average advance of 4.08 metres per month, and at a low cost of
£1.08 per metre. There was another exploration or ventilation shaft
sunk from surface for 8.23 metres during February 1858, after which the same
pare of two men drove north for 13.72 metres in the same month. It must
have been relatively soft ground, the rate per fathom for the shaft being £0.63
and for the drive £1.00.
Observations
It is difficult to make
comparisons between the costs per metre for shaft sinking without knowing the
cross sectional area of the shaft, rock conditions, ground water, depth of shaft,
type of hoisting and other factors. However it would seem that with hand
boring an average rate of 3 to 4 metres per month would be an acceptable
estimate for the larger shafts to a depth of 70 fathoms, with an extra two
months of time at each level for excavation of the plat and installation of a
penthouse, hanging tackle and ladder way.
Back to top
|